The District acquired approximately 43-acres adjacent to Cannan Ditch in an area that was identified in the District’s Master Drainage Plan as an area for regional detention. The District will be able to create approximately 280 acre-feet of detention capacity in an area that has had flood problems in the past.
Author: admin
Mykawa Drainage Project
This drainage project is part of the Texas Water Development Board grant program 75/25 local match agreement. The District was awarded the grant to enclose the ditch with reinforced concrete boxes and to construct mitigation ponds associated with the project. The goal of these improvements is to provide flood relief to the surrounding area and localized flooding which includes the neighborhoods of Willowcrest and Willowick.
Cannan Ditch Detention Pond
Pre-Construction
Under Construction
Longherridge Dr.
This is a joint partnership project with the City of Pearland that will replace a full 120′ run and a partial run of RCP that has separated. Both runs will be straighten out the 30″ RCP. The District will also realign the open ditch to the south which flows into Old Mary’s Creek.
Pre-Construction
In Progress
Construction Completed
Virtual Public Involvement Session
As part of a stormwater quality coalition effort, Brazoria Drainage District No. 4 will be hosting a Virtual Public Involvement Session to for input into the District’s Stormwater Management Program. The virtual session will be open starting July 1, 2022 – July 31, 2022.
Hickory Slough Improvements – Max Rd. to Silverlake Pkwy.
This purpose of this project is to clean out silt and repair the slopes as needed on Hickory Slough from Max Rd. to Silverlake Pkwy. The portion from Max Rd. to Cullen Blvd. will focus on the removal of silt islands and build up. Further west, from Cullen Blvd. to Silverlake Pkwy. the focus will be on slope repairs on the south side of Hickory Slough.
Pre-Construction
In Progress
Roy Rd. Detention Pond
The Roy Rd. Detention Pond project is located at the dead end of Roy Rd. adjacent to the south side of Clear Creek in Brookside Village. It will encompass the District acquired 14.335 acre Taha tract (purchased in FY 2020) and the previously acquired 4.13 acre Loonam tract allowing for a potential total of 18.465 surface acres of detention area and will provide additional flood mitigation for that area in Brookside Village.
Pre-Construction
Construction In Progress
Mary’s Creek Channel Lining @ Pearland Pkwy.
The District removed the failing rip-rap on the banks of Mary’s Creek at the bridge at Pearland Pkwy. and replaced it with concrete lining. The concrete will last a considerably longer length of time and allow for more efficient routine maintenance at that location.
Mary’s Creek Benching
The District will excavate benching areas along Mary’s Creek between FM 1128 & Magnolia Pkwy. These areas will expand the total capacity of the creek without causing a negative downstream or upstream impact.
This project is a precursor to the West Lea Ditch Improvements job.
Construction Complete
Orange St. Detention Pond
The Orange St. Detention Pond was constructed as mitigation for the Mykawa Drainage Improvement project which included installation of a double row of 4′ x 10′ RCBs. Completion of the Mykawa project enclosed the ditch on the west side of Mykawa from Cherry St. to Orange St.
This project is part of the Texas Water Development Board grant program 75/25 local match agreement. The District was awarded the grant to enclose the ditch with reinforced concrete boxes and to construct mitigation ponds associated with the project. The goal of these improvements is to provide flood relief to the surrounding area and localized flooding which includes the neighborhoods of Willowcrest and Willowick.