Completed Projects

Old Mary’s Creek Improvements

This project has been completed

This District project included clearing and reestablishing the banks along a section of approximately 1,400 linear feet of Old Mary’s Creek starting at the Mary’s Creek Bypass.

In Progress

Construction Completed

Moore Rd. Ditch Regrading

Mykawa Drainage Project

This project has been completed

This drainage project is part of the Texas Water Development Board grant program 75/25 local match agreement. The District was awarded the grant to enclose the ditch with reinforced concrete boxes and to construct mitigation ponds associated with the project. The goal of these improvements is to provide flood relief to the surrounding area and localized flooding which includes the neighborhoods of Willowcrest and Willowick.

Longherridge Dr.

This project has been completed

This project is part of a collaborative effort with the City of Pearland

This is a joint partnership project with the City of Pearland that will replace a full 120′ run and a partial run of RCP that has separated.  Both runs will be straighten out the 30″ RCP.  The District will also realign the open ditch to the south which flows into Old Mary’s Creek.

Pre-Construction

In Progress

Construction Completed

Hickory Slough Improvements – Max Rd. to Silverlake Pkwy.

This purpose of this project is to clean out silt and repair the slopes as needed on Hickory Slough from Max Rd. to Silverlake Pkwy.  The portion from Max Rd. to Cullen Blvd. will focus on the removal of silt islands and build up.  Further west, from Cullen Blvd. to Silverlake Pkwy. the focus will be on slope repairs on the south side of Hickory Slough.

Pre-Construction


In Progress


Mary’s Creek Channel Lining @ Pearland Pkwy.

This project has been completed

The District removed the failing rip-rap on the banks of Mary’s Creek at the bridge at Pearland Pkwy. and replaced it with concrete lining.  The concrete will last a considerably longer length of time and allow for more efficient routine maintenance at that location.

Mary’s Creek Benching

This project has been completed

The District will excavate benching areas along Mary’s Creek between FM 1128 & Magnolia Pkwy.  These areas will expand the total capacity of the creek without causing a negative downstream or upstream impact.

This project is a precursor to the West Lea Ditch Improvements job.

Construction Complete

Orange St. Detention Pond

This project has been completed

The Orange St. Detention Pond was constructed as mitigation for the Mykawa Drainage Improvement project which included installation of a double row of 4′ x 10′ RCBs.  Completion of the Mykawa project enclosed the ditch on the west side of Mykawa from Cherry St. to Orange St.

This project is part of the Texas Water Development Board grant program 75/25 local match agreement. The District was awarded the grant to enclose the ditch with reinforced concrete boxes and to construct mitigation ponds associated with the project. The goal of these improvements is to provide flood relief to the surrounding area and localized flooding which includes the neighborhoods of Willowcrest and Willowick.

Orange St. Pond - Before & After

Town Ditch Improvements – Old Alvin Rd. to Pearland Pkwy.

Town Ditch is being regraded and reseeded from Old Alvin Rd. to Pearland Pkwy. as part of the continued effort to improve drainage in the area.

In Progress

Construction Complete

Rogers Middle School Ditch

This project has been completed

Rogers Middle School Ditch was regraded and reseeded to improve flow and functionality.

Verified by ExactMetrics